KCS Civil served as Prime Civil Contractor for Lake Havasu City's Havasu Riviera Street & Utility Improvements project.  The project consisted of site development connecting two future developments: Havasu Riviera Arizona State Park and Havasu Riviera Residential Community.

Scope included:

  • Installation of 8,555 LF of 12" PVC waterline
  • Installation of 355 LF of 12" DIP water main
  • Installation of 13 fire hydrant assemblies
  • Installation of valves, bends, air/vac valves and associated pipeline appurtenances
  • Hot tap of existing 27" CCP water main
  • Backup power generation
  • Sewer lift station and SCADA
  • Odor control system
  • Security/screen wall and gates
  • Installation of 31,300 SY of four-inch asphalt roadway
  • Installation of 11,075 LF of concrete curb and gutter
  • Sawcutting and pavement removal
  • Installation of 26,765 SF of concrete sidewalk
  • Installation of 293 LF of 18" HDPE drainage pipe
  • Installation of 255 LF of 24" HDPE drainage pipe
  • Catch basins, riprap, and retaining walls
  • Installation of thirteen (13) 48" manholes


Owner: Lake Havasu City
Role: Prime Civil Contractor