SEDONA WASTEWATER RECLAMATION PLANT PV SYSTEM
Serving as General Contractor and Civil Subcontractor, KCS worked closely with Sun Edison and the City of Sedona to install a 661 kW DC photovoltaic system at the City of Sedona Wastewater Reclamation Plant. The City contracted direct with SunEdision through a Power Purchase Agreement (PPA) and the team successfully secured Production Based Incentives (PBI) through Arizona Public Service (APS). The photovoltaic system’s racking system is a pile-mounted, fixed-rack tilt system. KCS installed a total of 2,448 MEMC P270AMA QC and BizLink mixed-use generation one and generation two modules. KCS self-performed all site work scopes of work.
Size: 661 kW DC
Owner: City of Sedona
Role: General Contractor and Civil Subcontractor