Facing a compressed schedule, Kinney installed over 7,000 LF of conduit at three different campuses in less than four weeks. Working in close contact with the owners and engineers, Kinney implemented and installed cost-saving redesigns in a timely and efficient manner. Over 180 individual concrete spread footings were excavated into rock, and concrete was placed in under four weeks. Complete photovoltaic system installation totaled 1.45MW at the three campuses.
Facing a compressed schedule, Kinney installed over 7,000 LF of conduit at three different campuses in less than four weeks. Working in close contact with the owners and engineers, Kinney implemented and installed cost-saving redesigns in a timely and efficient manner. Over 180 individual concrete spread footings were excavated into rock, and concrete was placed in under four weeks. Complete photovoltaic system installation totaled 1.45MW at the three campuses.